Completion of 2nd Phase Tangled Wire Management Work

This is to notify you that we have successfully completed 2nd Phase Tangled Wire Management Work on February 28, 2025. Moreover, on behalf of Bafal Chowk Samaj (erstwhile Bafal Chowk Tole Sudhar Samiti), we would like to thank business organizations, shop owners and residents of Bafal, Gyanudaya Marg, Chinnalata Chowk for their contribution. Finally, we would also like to thank Mr. Sunny Deula and his technical team for their great effort to complete this 2nd Phase Project.

Project Name: Tangled Wire Management Work Chinnalata Chowk to Wal Marg- 2nd Phase

Project Start Date: Feb 23, 2025

Project End Date: Feb 28, 2025

Project Actual Cost:  Rs. 15,120/-


 

 

 